Chapter 2 — Software Processes & Process Models

(Sommerville Ch. 2)

What is a Software Process?

A software process is a structured set of activities required to develop a software system.

Major process activities:

  1. Specification — defining what the system should do
  2. Design and implementation — defining and building the system structure
  3. Validation — checking that it does what the customer wants
  4. Evolution — changing the system in response to customer needs

Plan-Driven vs. Agile Processes

1
2
3
4
5
6
7
8
9
10
Plan-Driven                          Agile
──────────────────────────           ──────────────────────────
All activities planned in            Incremental planning
advance                              
Requirements documented up           Requirements emerge through
front                                iteration
Change is costly                     Change is expected & welcomed
Suitable for large, stable           Suitable for changing,
requirements                         unclear requirements
Examples: Waterfall, RUP             Examples: Scrum, XP

The Waterfall Model

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
     ┌──────────────────────┐
     │  Requirements        │
     │  definition          │
     └──────────┬───────────┘
                │
     ┌──────────▼───────────┐
     │  System & software   │
     │  design              │
     └──────────┬───────────┘
                │
     ┌──────────▼───────────┐
     │  Implementation &    │
     │  unit testing        │
     └──────────┬───────────┘
                │
     ┌──────────▼───────────┐
     │  Integration &       │
     │  system testing      │
     └──────────┬───────────┘
                │
     ┌──────────▼───────────┐
     │  Operation &         │
     │  maintenance         │
     └──────────────────────┘

Pros:

  • Easy to manage — each phase has specific deliverables
  • Works well when requirements are very well understood
  • Good for large, safety-critical systems (aerospace, defense)

Cons:

  • Inflexible — difficult to respond to changing requirements
  • Working software not produced until late in the lifecycle
  • Requirements rarely fully known at project start

Phase entry/exit criteria (Classical Waterfall):

  • Entry: Previous phase fully documented and signed off
  • Exit: Current phase deliverables reviewed and accepted by stakeholders

Boehm’s Spiral Model

1
2
3
4
5
6
7
8
9
10
11
12
              Determine objectives,
              alternatives, constraints
   4th ◄──────────────────────────────── 1st
   quadrant                          quadrant
   Plan next                         Identify and
   iteration                         resolve risks
   ▲                                       ▼
   3rd                               2nd
   quadrant                          quadrant
   Develop and                       Evaluate
   validate next                     alternatives
   level ─────────────────────────►

The spiral is divided into 4 quadrants, repeated across growing spirals:

QuadrantActivities
1. Objective settingIdentify objectives, constraints, alternatives
2. Risk assessmentIdentify and resolve risks; may involve prototyping
3. Development & validationChoose a development model; build and test
4. PlanningReview with the client; plan the next iteration

Key concept: Each loop of the spiral represents a phase of the software process. Risk is explicitly addressed at every iteration.

Can also be used for: planning iterative development of large systems where risk is high, or for systems where requirements are unclear.

SDLC Framework Activities

  1. Communication — customer communication and requirements gathering
  2. Planning — project plan, resource estimation, scheduling
  3. Modeling — analysis and design
  4. Construction — coding and testing
  5. Deployment — delivery and feedback

Evolutionary Development

In evolutionary development, initial implementation is built quickly, then refined through feedback. Problem: The process is not visible; it’s hard to track progress. Systems are often poorly structured because continuous change degrades the architecture — making them difficult to maintain.

“Programs developed using evolutionary development are likely to be difficult to maintain because there is no overall structure — they become a patchwork of changes.”

This post is licensed under CC BY 4.0 by the author.